Extending a consent's lapse date (s125)

An application by a resource consent holder for more time to give effect to the consent before it lapses.[1][2][3]

Last reviewed 12 Oct 2026. This page explains the usual process in general terms. It is not legal advice; the council's decision documents govern any particular application.

New Zealand is replacing the Resource Management Act 1991 with the Planning Act 2026 and the Natural Environment Act 2026. The transition period starts on 30 October 2026. Resource consent applications lodged before then continue under the Resource Management Act as it was before the Planning Act 2026 received royal assent. Applications lodged during the transition are processed under the Resource Management Act as in force when they are lodged. This page will be updated when that changes.[4][5][6]

What this application is

Under section 125 of the Resource Management Act 1991, a resource consent lapses on the date stated in the consent. If the consent states no date, it lapses 5 years after it commences, or 3 years for a consent for aquaculture activities in the coastal marine area and 10 years for a consent for a renewable energy activity. Both councils say that in most cases a consent holder has 5 years from the day the consent is granted, and that the consent itself should be checked for any specific time frame.[1][2][3]

A consent does not lapse if, before it lapses, it is given effect to, or the holder applies to the council for an extension and the council decides to grant one. A separate provision lets the council shorten the lapse period of a renewable energy consent at the holder's request. For a subdivision consent, section 125(2) says the consent is given effect to when a survey plan is submitted to the council under section 223, but it then lapses if the survey plan is not deposited in accordance with section 224.[1]

When deciding whether to grant an extension, section 125(1A) says the council must take into account whether substantial progress or effort has been, and continues to be, made towards giving effect to the consent; whether the applicant has obtained approval from persons who may be adversely affected by the extension; and the effect of the extension on the policies and objectives of any plan or proposed plan.[1]

An extension application in a council's list shows that the consent holder asked for more time, not that the extension was granted. Wellington City Council says a granted extension comes with a new lapse date and that, unless the holder has also applied to change the conditions, all the requirements of the original consent stay the same.[2][3]

Auckland Council says that if a consent lapses before an extension has been approved, the holder will need to apply for a new resource consent. Wellington City Council says a new resource consent is needed if the consent lapses before the holder applies for an extension, or if the extension is declined.[2][3]

What neighbours can do

Auckland Council publishes a weekly list of resource consent applications lodged in the last 26 weeks, and its Regional Planning Helpdesk can give details about specific applications. Wellington City Council says resource consent applications are public information and anyone can ask it for a copy of a recent consent.[7][8]

Section 125 asks the council to consider whether the applicant has obtained approval from persons who may be adversely affected by the extension. Wellington City Council says an extension application must include the written approval of anyone considered affected by granting it. Both councils say the planner deciding the application considers whether anyone is likely to be affected by the extension.[1][2][3]

Notification

Section 125 does not set out notification or submission steps for an extension application. Section 127(3) applies the usual resource consent provisions, including notification, to applications to change consent conditions, but section 125 has no equivalent provision. Section 125(1A) requires the council to take into account whether the applicant has obtained approval from persons who may be adversely affected.[1][9]

Neither council's extension page describes a notification step. Both say a planner considers the application and makes a decision. Auckland Council says it processes extension applications within 20 working days, and Wellington City Council says the process takes up to 20 working days, or longer if it needs more information.[2][3]

In Auckland

Auckland Council recommends applying at least six months before the consent lapses, and says the applicant needs to show considerable efforts to fulfil the purpose and conditions of the consent. It says a planner decides based on the progress made, whether anyone is likely to be affected by the extension, and whether the Unitary Plan has changed since the consent was granted. It accepts extension applications only online.[2]

In Wellington City

Wellington City Council says the application must be made before the consent lapses and must include a statement of how much extra time is sought, a timeline of the progress made since the consent was granted, the written approval of anyone considered affected, and an assessment of the extension's effects on the policies and objectives of any District Plan or Proposed District Plan.[3]

Wellington City Council says a planner decides based on the progress or effort made towards implementing the consent, whether anyone is likely to be affected by the extension, and whether the District Plan has changed since the consent was granted.[3]

Read the council's own guidance

Sources

  1. Resource Management Act 1991, section 125: Lapsing of consents, New Zealand Legislation (Parliamentary Counsel Office) (accessed 2026-10-12)
  2. Extension of time of a resource consent, Auckland Council (accessed 2026-10-12)
  3. Applying for an extension of time, Wellington City Council (accessed 2026-10-12)
  4. Planning Act 2026, Schedule 1 (transitional, savings, and related provisions), clauses 3, 18 and 19, New Zealand Legislation (Parliamentary Counsel Office) (accessed 2026-10-12)
  5. Planning Bill and Natural Environment Bill pass Third Reading, Ministry for Cities, Environment, Regions and Transport (accessed 2026-10-12)
  6. The Planning Act 2026 and Natural Environment Act 2026 are in force: What you need to know now, MinterEllison (accessed 2026-10-12)
  7. Recent resource consent applications, Auckland Council (accessed 2026-10-12)
  8. Recent resource consents, Wellington City Council (accessed 2026-10-12)
  9. Resource Management Act 1991, section 127: Change or cancellation of consent condition on application by consent holder, New Zealand Legislation (Parliamentary Counsel Office) (accessed 2026-10-12)

Applications NearBuild has recorded

Auckland

NearBuild holds 244 applications of this kind from Auckland Council's list, lodged between 23 Feb 2026 and 23 Oct 2026. That is 3% of the Auckland applications NearBuild holds.

Council wording included
Council wordingApplications
Extension of lapse date244

Lapse date extensions per month in Auckland

  1. 7 (partial month)
  2. 19
  3. 27
  4. 25
  5. 30
  6. 37
  7. 50
  8. 29
  9. 20 (partial month)

A partial month is one where NearBuild's records start part-way through it or stop before it ends.

Suburbs with the most applications of this type

  1. Manurewa (12)
  2. Waiheke Island (11)
  3. Mount Roskill (9)
  4. Drury (8)
  5. Massey (8)
  6. Glenfield (7)
  7. Henderson (7)
  8. Parnell (7)
  9. Birkenhead (6)
  10. Flat Bush (5)

Latest recorded applications

402B Orapiu Road Waiheke Island Auckland

402B Orapiu Road Waiheke Island Auckland

27 Moire Road Massey

27 Moire Road Massey

2 Sunlands Drive Manurewa Auckland

2 Sunlands Drive Manurewa Auckland

29 Don McKinnon Drive Albany 0632

847 New North Road Mount Albert Auckland

29 Don McKinnon Drive Albany 0632

4 Skanda Crescent Flat Bush 2016

7 Sheehan Road Te Atatu South

7 Sheehan Road Te Atatu South

151 Ocean View Road Waiheke Island Auckland 1081

4 Skanda Crescent Flat Bush 2016

4 Skanda Crescent Flat Bush 2016

58 Royal Road Massey

58 Royal Road Massey

11 Poutini Place Manurewa Auckland

11 Poutini Place Manurewa Auckland

39 Bel Air Drive Hillsborough Auckland

Source and sync
SourceAuckland Council — Recent resource consent applications Data last updated
SourceWellington City Council — Recent resource consents Data last updated

Contains data from Wellington City Council, licensed under CC BY 4.0. CC BY 4.0 licence

Record fetched: .